Globe NewswireOther News

Victoria Gold: Update on Eagle Gold Mine

125

WHITEHORSE, Yukon, July 12, 2024 – Victoria Gold Corp. (TSX-VGCX) (“Victoria” or the “Company”) provides a further update on the heap leach facility (“HLF”) incident that occurred at the Eagle Gold Mine on June 24, 2024 (see Company News Releases dated June 24, 2024 and July 4, 2024).

Victoria’s focus continues to be on the safety of its employees and mitigation of harm to the environment. As previously reported, the Company has and will continue to liaise with the Government of Yukon, the First Nation of Nacho Nyak Dun (“FNNND”), the Village of Mayo, the Yukon Workers’ Safety and Compensation Board and other regulatory authorities.

Mitigation

With respect to environmental mitigation, as previously disclosed, within hours of the incident a pumping system was established to return water from the HLF material to lined containment ponds. Diversion systems have also been installed for the management of both non-contact and contact water and material.

Water Sampling

Victoria is actively sampling water daily from multiple sample locations at the Eagle mine. Several of these sample locations are located downstream from the location of the HLF incident. Final results received subsequent to the Company’s News Release dated July 4, 2024, showed one trace detection of cyanide in one of the downstream sample results from Haggart Creek collected on July 2, with the sample measuring 5.7 parts per billion total CN. Prior to July 2, and subsequently on July 3 and July 4, samples collected at this sample location did not detect any cyanide.

Other than this one sample, there has been no other detection of cyanide in final results at any of the water quality objective sampling locations received as of July 10, 2024 by the Company, which include samples collected up to July 4, 2024. For further clarity, as of July 4, 2024, based on final sampling results received by the Company, the Company has not exceeded its Downstream Water Quality Objectives pursuant to its Water Use License.

Heap Leach Facility and Infrastructure

Since the start of production, approximately 38.9 million tonnes of ore has been stacked on the HLF. Based on an independent survey of the HLF, the Company estimates that approximately 4 million tonnes of ore, representing about 10% of the total ore tonnes within the HLF, moved during the HLF incident. Of this 4 million tonnes, the Company estimates that approximately half, or 2 million tonnes of ore, representing about 5% of the total ore tonnes within the HLF, moved beyond the HLF embankment. The Company has developed a plan to stabilize the HLF which is under review by an independent third party.

The majority of on-site infrastructure was not affected by the HLF incident. The Eagle open pit, associated mining infrastructure and mobile equipment, primary crusher, secondary and tertiary crushers, main overland conveyor, ADR plant, lined water containment ponds, water treatment plant, warehouse facilities, and camp and office complex were unaffected by the incident. Based on observations to date, on-site infrastructure on or near the HLF that has been impacted includes the HLF embankment, piping, pumping, liner, two short lengths of fixed conveyors, as well as a small amount of electrical infrastructure.

Root Cause Analysis

Investigations are underway to determine the cause of the incident. The Company has engaged with its engineer of record for the HLF and is cooperating with 3rd party technical experts retained by the Yukon Government and the FNNND.

Production operations remain suspended and may not restart without authorization from the Yukon Director of Mineral Resources. Victoria will continue to work to minimize impacts to the environment, with the safety of employees as a foremost priority. There can be no assurance that the Company will receive authorizations necessary to restart production, or that the Company will have the financial resources necessary to repair damage to equipment and facilities or remediate impacts caused by the incident or restart production. The Company will provide further updates in due course.

Aerial view of Eagle Gold mine – extent of June 24, 2024 HLF incident outlined in yellow

Aerial view of Eagle Gold mine - extent of June 24, 2024 HLF incident outlined in yellow

Qualified Person
The technical content of this news release has been reviewed and approved by Paul D. Gray, P.Geo., who is a “Qualified Person” as defined in National Instrument 43-101 – Standards of Disclosure for Mineral Projects.

Related Articles

Globe NewswireLifestyle, Fashion & WellnessLNA World

Must-Have Holiday Gift: Exotic Snack Guys Mystery Box Takes Center Stage

Exotic Snack Guys offers unique Mystery Gift Boxes featuring international snacks and...

AutomotiveGlobe NewswireLNA World

Motiv Electric Trucks Crosses 5 Million Mile Mark

Nearly 400 electric trucks, trolleys and buses collectively have reduced more than...

BusinessFinanceGlobe NewswireLNA World

Bybit One-Click Buy Offers a Winning Chance in First-Time Deposits Lucky Draws

DUBAI, United Arab Emirates, Dec. 20, 2024 – Bybit, the world’s second-largest cryptocurrency...